– New Spanish slate roof
– breathable membrane installed
– All new zinc ridging
– 6x dormers wrapped in VM zinc
– 4 x coping wall wrapped in VM zinc
– 12x Schues VM zinc
– 12x valleys VM zinc
– Turret 1/4 Vm zinc
– Turret 3/4 slate
– Turret base , lead
– Turret gutter fabricated to fit
– Turret cone fabricated to fit
– New Pvc deep flow gutters on all dormers and front & back elevation
– New soil pipes installed
– All new bargeboard on dormers
– All sarcan repaired and installed were necessary
– The customer had all windows revamped and painted to suit the new dormers

All lead flashings renewed at chimneys